11/23/09: STS-129: Bresnik and Satcher complete all tasks of today's spacewalk.
Mission Control Center Status Report #15
3 p.m. CST Monday, Nov. 23, 2009
, Mission Control Center, Houston, Texas
Mission: STS-129
Orbiter: Atlantis
Launch Pad: 39A
Launch Date: NET Nov 16, 2009, 14:28:09 EST (19:28:09 UT)
Landing: Nov 27, 2009
Main gear touchdown: 09:44:23 EST
Nose gear touchdown: 09:44:36 EST
Wheels stop: 09:45:05 EST
Orbital Altitude: 122 nautical miles (140 miles)
Orbital Insertion: 191 nautical miles (220 miles)
Orbital Inclination: 51.6 degrees
Distance traveled: ~4.5 million miles
Crew:- Commander: Charles O. Hobaugh; Pilot: Barry E. Wilmore; Mission Specialists:- MS1 Leland D Melvin, MS2 Randolph Bresnik, MS3 Michael Foreman, MS4 Robert Satcher, MS5 (landing) Nicole Stott.
Primary Payload: ExPRESS (Expedite the Processing of Experiments to the Space Station) Logistics Carriers ELC1 and ELC2:-
ExPRESS Logistics Carrier-1 manifest:- Ammonia Tank Assembly; Battery Charge Discharge Unit; Space Station Remote Manipulator System Latching End Effector; Control Moment Gyro; Nitrogen Tank Assembly; Pump Module; Plasma Contactor Unit; two empty Passive Flight Releasable Attachment Mechanisms.
ExPRESS Logistics Carrier-2 manifest:- High Pressure Gas Tank; Cargo Transport Container 1 (CTC-1) mounted to a Small Adapter Plate Assembly; Mobile Transporter/Trailing Umbilical System; Control Moment Gyro; Nitrogen Tank Assembly; Pump Module; Utility Transfer Assembly (UTA) Flight Support Equipment (FSE); one empty Payload Passive Flight Releasable Attachment Mechanism.
Astronauts Randy Bresnik and Robert Satcher Jr. completed all the tasks of their spacewalk almost on its original schedule despite a late start.
The spacewalk was the third and final spacewalk scheduled during Atlantis’ mission to the International Space Station. It ended at 1:06 p.m. CST, lasting five hours and 42 minutes.
Intravehicular officer, coaching the spacewalkers from inside the station, was Mission Specialist Mike Foreman, who participated in the Thursday and Saturday spacewalks. Astronauts Leland Melvin and Barry Wilmore operated the station’s robotic Canadarm2.
It played a major role in the spacewalk’s first and most lengthy task, the installation of a 6.2-foot-long, 1,240-pound high-pressure oxygen tank. The arm lifted the tank from Express Logistics Carrier 2 (ELC2) and took it to the airlock, where it was attached. It joined four similar doghouse-shaped tanks, two oxygen and two nitrogen, on the airlock’s rim.
While Satcher worked on early steps of the tank move, Bresnik got a materials experiment from Atlantis’ cargo bay and installed it on ELC2. That Materials ISS Experiment 7 exposes a variety of materials in two containers, much like open suitcases, to the harsh conditions of space for several months. Some of those materials could find application on future spacecraft and on Earth.
The two also removed some debris shields from outside the airlock and strapped them to an external stowage platform. Bresnik relocated a foot restraint.
Satcher released a bolt on an ammonia tank in preparation for a spacewalk during the STS-131 mission next year to replace the tank. It is part of the station’s cooling system. He approached the task equipped with a cheater bar to provide additional leverage. It was not needed. He stowed the bar on the outside of the station for possible future use.
Satcher installed insulated covers on cameras on the mobile servicing system and on Canadarm2’s end effector, the latching hand.
Meanwhile Bresnik installed a fluid jumper at the interface of the Port 1 and Port 3 truss segments, then did a similar task at Starboard 1/Starboard 3.
The spacewalk initially had been scheduled for 6.5 hours, including 45 minutes of contingency time. It began more than an hour later than planned because a drinking-water valve in Satcher’s suit became dislodged. The helmet had to be opened to reattach the valve, disrupting the spacewalk preparation process.
The next shuttle status report will be issued after crew wakeup, or earlier if events warrant.
Nov 23: Astronaut Robert L. Satcher Jr., STS-129 mission specialist, participates in the mission's third and final session of extravehicular activity (EVA) as construction and maintenance continue on the International Space Station. During the five-hour, 42-minute spacewalk, Satcher and astronaut Randy Bresnik (out of frame), mission specialist, removed a pair of micrometeoroid and orbital debris shields from the Quest airlock and strapped them to the External Stowage Platform #2, then moved an articulating foot restraint to the airlock, and released a bolt on a starboard truss ammonia tank assembly (ATA) in preparation for an STS-131 spacewalk that will replace the ATA. Credit: NASA
- courtesy of NASA
Space and Astronautics News is completely opposed to the use of any animals in science experiments, including in space missions.
Timezones:
EST = (UT - 5 hours)
EDT = (UT - 4 hours) = (CDT + 1 hour)
CST = (UT - 6 hours)
CDT = (EDT - 1 hour) = (UT - 5 hours)
PST = (UT - 8 hours)
PDT = (UT - 7 hours)
MDT = (UT - 6 hours)
UT [GMT] = (EDT + 4 hours)
BST = (EDT + 5 hours) or (CDT + 6 hours) = (UT + 1 hour)
CEST = (UT + 2 hours) = (BST + 1 hour)
EDT, CDT, PDT, MDT daylight saving time = EST, CST, PST, MST +1hr. From 2007, this begins on the second Sunday in March, and ends on the first Sunday in November.
[Until 2007, EDT, CDT, PDT, MDT used to start at 02:00 local time on the first Sunday in April. EST, CST, PST started at 02:00 local time on the last Sunday in October.]
UT is also known as GMT (Greenwich Mean Time), Z, and UTC (Coordinated Universal Time). It is the time set on the International Space Station.
*Where '/' appears in dates, this site follows the following format: mm/dd/yr
Copyright © Space and Astronautics News 1999 - 2010 All Rights Reserved.
|